Category Archives: Finished Projects
Methane Station, “Petrol”, Varna
In May 2010 of an existing station of “Petrol” with address: city of Varna, “Briz” distr., reconstruction was performed and mounted compressor type “Microbox Gallileo” MXL 185-4-1500-5 with power 135 kW, 4 degrees, 1,500 rpm and maximum consumption of 900 nm ³ / h. The supply of gas station is performed via central pipeline with working pressure of 1.6 MPa. With this reconstruction of the facility the capacity increases to 2100 nm ³ / h.
GAS INSTALLATION “TOPLIVO” JSC, BURGAS
In 2010 GASTEH BG Ltd. organized the delivery and installation of a pumping unit for road tankers in tanks to supply the plant for filling bottles with domestic LPG owned by “Toplivo” JSC, located in “LUKOIL”, Burgas. Gas installation was designed by the engineer Lyubomir Arsov /arsov@nsc-bg.com /.
The gasification of the asphalt base of “Road Engineering” JSC
The gasification of the asphalt base of “Road Engineering” JSC has been designed in February 2010 by the team of “GASTEH BG” LTD. The gas plant was built in March and 14th of April was put into operation.