Unloading point for propane-butane, city of Dobrich – 2
In May 2011 was finished also the second stage, including the finalization of the rail unloading platform, thus increasing its capacity up to servicing 15 rail tankers. A second compressor BLACKMER LB601L with a capacity of 108 m³/h as well as a pump SIHI UEA8006 with a capacity of 60 m³/h were supplied and installed. Furthermore were installed 3 tanks for propane-butane, 260 m³ each. The unloading point works also as a tax registered storage. The companies participating in the construction have implemented quality management systems complying to international standards – ISO 9001:2008, ISO 14001:2004 and HSAS 18001:2007.