Gasification of glass factory Claire-D Ltd
In January2012 design team of GASTEH BG Ltd. issued a working project for object: Gas installation of industrial building-glassworkshopof ”Claire-D” Ltd., Sofia, Orlandovci, Street First Bulgarian Army № 17.
The project was completed and commissioned in the April 2012. Constructed industrial gas installation powered machine laminated glass panelsin the workshop and has built adiversion to theboiler roomof the company.
Industrial gas installation has the following parameters:
- Working pressure industrial gas installation – 4 [bar];
- Working pressure industrial gas installation deviation workshop – 100 [mbar];
- Working pressure industrial gas installation deviation boiler room – 20 [mbar];